Staff recommends $156,950 contract for Woodhaven Drive slip remediation

Huntington City Council · December 23, 2024

Get AI-powered insights, summaries, and transcripts

Subscribe
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Public Works Director Mark Bates recommended awarding the Woodhaven Drive slip remediation contract to Allen Stone Company (Vincent, Ohio) for $156,950 after receiving three bids; funding will come from the Public Works Street Construction General Fund Budget.

Mark Bates, Huntington’s public works director, presented a contract recommendation on Dec. 23 to repair a slip on Woodhaven Drive (project date listed as Oct. 30, 2024). Purchasing received three bids: Allen Stone Company of Vincent, Ohio ($156,950); Benchmark Construction Company of Hurricane, West Virginia ($323,000); and Thaxton Construction Company of Charleston (amount unclear in the transcript). Bates recommended contracting with Allen Stone for $156,950, with funding from the Public Works Street Construction General Fund Budget.

Bates said the bid is for construction of a pile and lagging wall along Woodhaven Drive and that the parcels described earlier in the meeting were roadway or right-of-way rather than occupied structures. He invited questions from council; none were recorded in the transcript.

The resolution presented seeks council authorization for the mayor to enter into the contract; the transcript records the recommendation and the bid amounts as presented but does not include a formal recorded vote.