Council approves Amendment No. 2 to Stewart Park Drive bridge IGA after bid overruns

Roseburg City Council · November 18, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council authorized Amendment No. 2 to the ODOT IGA for rehabilitation of the Stewart Park Drive/South Umpqua River bridge, increasing total project cost to $6.32 million; the city’s matching share rises by $56,679 but ODOT covers most overruns.

Roseburg’s City Council on Nov. 18 authorized Amendment No. 2 to the intergovernmental agreement (IGA) with the Oregon Department of Transportation (ODOT) for the rehabilitation of the Stewart Park Drive bridge over the South Umpqua River.

Staff said the bridge — built in 1933 with a current sufficiency rating of 16.1 out of 100 and a reduced load rating of 12 tons (previously 34 tons) — was bid over engineer’s estimate. Amendment No. 2 raises the total project cost from $5,770,000 (post‑amendment 1) to $6,321,890.07. ODOT’s local bridge program covered most of the overrun; the city’s additional match for this amendment is $56,679, bringing the city’s required match to $649,258.11. Staff warned that if the city declined to provide the additional match, ODOT could cancel the project and potentially require the city to reimburse roughly $1.1 million in incurred costs to date.

The project scope includes steel sandblasting and painting, deck repair, strengthening pin-and-hanger connections, sidewalk and ADA approach upgrades and replacement of damaged structural members. Staff reported federal funds cover $5,672,631.96 of the project; the contractor selection process and the public‑works commission’s unanimous recommendation to proceed were noted.

What’s next: With council authorization, staff will execute the amendment and proceed with ODOT’s notice to proceed and construction schedule. Staff said emergency-response fire engines (single rear-axle, 22 tons) will be able to cross the rehabilitated bridge, though the ladder truck (39 tons) will still not be cleared.