Planning staff reported more than 1,000 public contacts and survey responses for the "Montgomery Matters" comprehensive-plan update and identified housing supply, flood-hazard mapping and broadband deployment as priority issues; next stakeholder meetings are scheduled for the week of Oct. 21.
Get email alerts on the Comprehensive Plan topic
No spam. Unsubscribe anytime.
Justin, the county planning director, gave the Planning Commission a progress report on the "Montgomery Matters" comprehensive-plan update at the Oct. 9 meeting, summarizing public engagement, data sources and early recommendations. "We spoke with over a thousand individual citizens at those events," Justin said, describing outreach at festivals, public intercepts and two rounds of stakeholder meetings.
Staff said they used multiple data sources for analysis, including the 2020 decennial census, the American Community Survey, population estimates from the Weldon Cooper Center and local building-permit data. Justin told commissioners the county also selected benchmark communities (Albemarle and Rockingham counties in Virginia, and Orange County, North Carolina) to compare trends and inform policy choices.
Key findings and draft priorities presented to the commission included an aging housing stock, a persistent renter cost burden in denser areas, and a forecasted need for additional housing units through 2040–2050. Justin said staff recommend exploring a wider range of housing types beyond single-family homes and conventional apartments — including duplexes, triplexes and fourplexes — and coordinating with town partners to address density in growth areas.
The presentation highlighted environmental resources and flood hazards: staff showed maps of conserved lands, parks and pollution heat maps, and consultants recommended greater attention to non-point-source pollutants such as agricultural runoff. Justin said village plans for Elston, Lafayette and Shawesville are largely silent on flood hazards and recommended adding goals to address repetitive flooding and mitigation.
On broadband, county staff briefed the commission on two VADI fiber grants the county secured. Justin said the county's broadband rollout is dependent in part on AEP crews and that storm damage has slowed deployment in some areas; satellite partnerships and providers such as GigaBeam will be used where fiber is not feasible.
Justin outlined next steps: staff will hold another round of stakeholder meetings during the week of Oct. 21, a public open house and workshop in November, and produce a "state of the county" report to inform goal development. He also provided a flood-recovery update, noting roughly 20 structures damaged or lost in the most affected areas, and an interactive GIS tool to show residents which addresses have had boil-water notices lifted.
The commission discussed data currency, benchmarking choices, and coordination with the towns and infrastructure providers. No formal plan decisions were taken at the meeting; staff said recommendations and draft goals will be refined through further community input and upcoming meetings.