County awards $521,920 transfer-station slab contract, approves $530,992 supplemental appropriation
Summary
After receiving a single responsive bid, Washington County awarded Quisenberry's Construction a $521,920 contract to replace interior (and optionally exterior) concrete slabs at the transfer station and approved a $530,992 supplemental appropriation from capital improvement funds to cover the work and related carryover balances.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
Washington County staff recommended awarding a contract to Quisenberry's Construction for $521,920 to replace the interior slab — and optionally the exterior slab — at the county transfer station. Tammy (Mr. Berry and staff) told the board the county solicited bids, held a mandatory pre-bid meeting, and received only one responsive bid. Staff said they contacted other contractors; one replied that the project's timeframe exceeded their available resources. The bidder was deemed responsive and responsible and the price was judged fair given the schedule.
The bid included a lump-sum base of $339,500 for demolition and replacement of the interior slab, an additive alternative of $180,500 for exterior slab replacement, and unit pricing for stone and unsuitable soil replacement. Staff proposed a supplemental appropriation of $530,992 using two capital-improvement line items that originate from prior-year carryover ($104,793 and $426,199).
Board members discussed operational impacts during construction: staff warned the station likely would have to be shut down for approximately two weeks, possibly up to three, and trash would be directed under contract to a Tennessee landfill for that period. Supervisors requested prominent signage and advance notice to residents; staff agreed to issue a press release and reduce disruption where possible by scheduling work and keeping high-traffic convenience sites open.
A motion to award the contract to Quisenberry's Construction for $521,920, authorize Mr. Berry to sign the contract, and approve the $530,992 supplemental appropriation was moved and passed by recorded vote.