County reports reservoir pumping delay, green-energy sites cleared for land disturbance

Cumberland County Planning Commission · September 16, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Staff said a two-week hold on the concrete reservoir expired but low James River levels are preventing pumping; land-disturbance permits for two previously approved solar sites (Dunn and Rowlett Sites 1 and 2) were approved and construction or clearing is expected in about two weeks.

County planning staff told commissioners that while a two-week operational hold at the county’s concrete reservoir has ended, currently low James River levels prevent pumping into the reservoir. Staff said they expect impending rain could allow pumping to resume in the coming days.

Separately, staff said conditional-use permits issued in 2021 and 2022 for Dunn and Rowlett Sites 1 and 2 now have cleared land-disturbance approvals. "They will begin construction or land clearing, in about 2 weeks," Unidentified Speaker 2 said, and staff scheduled a reconstruction meeting for Oct. 1 to coordinate next steps.

The solar land-disturbance approvals will be reflected in future monthly permit reports, staff added. No new funding commitments or formal approvals by the commission were reported at the meeting.