Commissioners weigh per-well, per-mile road impact fees; consultants propose options from $27,900 to $18,400

Duchesne County Commission · October 7, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

In a work session, county staff and consultants presented a transportation mitigation fee for oil-and-gas activity that ranged from an initial engineering estimate of $40,600 per well per mile down to $27,900 after a statistical adjustment; additional options (county covering some items and using overlays for half of roads) could lower the figure to about $23,000 or $18,400 per well per mile.

Duchesne County commissioners heard a technical briefing Oct. 7 on a proposed transportation mitigation fee to recover industry road impacts from oil-and-gas development. Jones & DeMille and county engineers presented a formula-based approach using pavement structural analysis and sample road cores across the county.

The initial detailed estimate used a conservative 95% reliability factor and produced a per-well, per-mile replacement cost of about $40,600. Consultants explained that using a 90% reliability (a standard for major/minor collectors per UDOT methodology) reduces that figure to $27,900 per well per mile. Further scenario adjustments — where the county would cover the 20% "items not estimated" (signage, drainage and other contingencies) and assume half the impacted roads could be addressed with a 4-inch overlay rather than full reconstruction — would reduce the charge to approximately $23,000 per well per mile; a mixed-overlay/reconstruction scenario could bring the number down further to about $18,400.

Commissioners discussed potential policy options including mileage caps, capping the fee at a set mileage, offering credits if industry pre-upgrades a road, and whether fees should be reduced where the county elects to cover certain non-structural items. Industry representatives requested the underlying data and a third-party verification; staff said they would provide exportable spreadsheets and a map showing where cores were taken and which roads industry expects to use.

No final ordinance vote occurred; commissioners directed staff and the consultant to provide written scenarios and clarified estimates for the next meeting, including sample road-by-road cost comparisons and an exhibit overlaying industry proposed haul routes with the county’s pavement core locations.