Board approves FBO lease expansion and new site; Leading Edge outlines phased terminal plan

Cache County Airport Authority Board · November 7, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Leading Edge Aviation outlined a three-phase plan to relocate its FBO building, add a 12,000 sq. ft. hangar and build a new terminal; the board approved a lease expansion and a new site for the maintenance shop and directed owners to pursue planning commission steps.

Leading Edge Aviation asked the Cache County Airport Authority Board for permission to move its existing fixed-base operator building to a new on-airport location, construct a 12,000-square-foot hangar and build a new terminal. The board voted to approve a lease expansion and a new site for the proposed maintenance shop.

Scott Weaver, representing Leading Edge, described a three-phase approach: complete engineering drawings and permits, relocate the existing FBO and foundation work (targeted for summer/fall 2025) and construct a new terminal (targeted for summer 2026). "We're asking for your support this morning to first, move our current FBO building to a new location on the airport, and then construct a new modern FBO terminal," Weaver said.

Architect Chris Slayton described design goals including an aeronautic-inspired palette, insulated metal panels and glass, and ancillary spaces for charter and business conferencing. Board members asked about the exact footprint, parking impacts and temporary relocation logistics; Weaver said the relocated building would be placed on a new 6-foot concrete foundation and the owners plan to repurpose the relocated building for piston maintenance and later turbine maintenance.

A board member moved and another seconded a motion to approve the lease expansion and the new site for the maintenance shop; the motion passed on a voice vote. Board members advised the applicants to coordinate with Logan City planning commission next, noting it can take about a month to get on the planning agenda.

Next steps: Leading Edge will pursue engineering, permitting and planning-commission review and work with the airport manager on lease terms and site details before construction.