Neshaminy SD board approves $413,289 change order and 121-day extension for Core Creek Elementary
Summary
The Neshaminy School District Board approved a change order adding $413,289.10 to the Core Creek Elementary construction contract and extended the substantial completion date by 121 days to Nov. 30, 2024; the measure passed 7–0.
Get email alerts on the Construction Change Order topic
No spam. Unsubscribe anytime.
Neshaminy SD Board of School Directors voted to approve a construction change order for Core Creek Elementary that increases the contract by $413,289.10 and extends the substantial completion date by 121 days, to Nov. 30, 2024.
Mister Allen, a board member, introduced the motion, saying the additional costs stemmed from rework of already-excavated footings, the remobilization of a crane and the need for temporary heating during work. The board chair called for a second; Miss Lafferty seconded the motion. After no further comment, the board approved the measure by voice vote, 7–0.
The motion authorizes the district business administrator to execute the attached change order with ER Stubner (contractor name as stated in the materials). The agenda materials recorded that the change order had been reviewed and approved by the district solicitor. No public speakers or amendments were recorded during the discussion.
The board’s action follows standard construction-change practices noted in the agenda: change orders may be required when unforeseen site conditions or permit-related issues lead to additional work. The new completion date, as read into the record, is Nov. 30, 2024; the materials cited an additional cost of $413,289.10.
Next steps: the business administrator is authorized to finalize and sign the change order; the district did not record any further schedule or cost contingencies in the public discussion.