Superintendent reports steady progress on new K–6 school; interior work to continue after exterior looks complete
Summary
School officials reported that concrete floors and block walls for the new K–6 elementary school are in place, roof installation is planned before Christmas and contractors project substantial completion around January 2025; the board was invited to schedule a site tour after stairs are installed.
Get email alerts on the Education Infrastructure topic
No spam. Unsubscribe anytime.
Brunswick County Schools provided a construction update on the new K–6 elementary school sited on Planters Road.
Dr. Carter reviewed milestones: classroom concrete floors have been poured, block walls are being built, door and window frames are being installed, and the main entrance and administrative areas are the current focus. McBcon (construction manager at risk) and owner representative Skanska reported work is meeting schedule expectations. Utilities work (sewer, water, electrical) remains a near‑term priority for site connection; the contractor expects stairs to be installed by mid‑November and roof installation to begin before Christmas, with the project under roof in January. Dr. Carter said the projected completion window is late fall/early winter 2024–25 with an expected completion by January 2025, but actual occupancy will depend on final inspections and interior finishing.
Dr. Carter also summarized related work at the high school: ABM completed bathroom renovations in summer 2024 and the next phase includes HVAC, lighting and painting upgrades in 19 upstairs classrooms with a projected completion of April 2025 for those areas. Board members asked about tours and were invited to arrange site visits with the county administrator and superintendent once stairs are finished to improve accessibility.
Representative quote: “Everything they’re doing is meeting the deadlines, so we feel good about their progress,” Dr. Carter told the board.
No construction contract changes were approved at the meeting; the report was informational and the board thanked school staff for the update.