Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
Commission tables McKinley contract, allocates $668,524 toward animal-control facility
Summary
After debate over a percentage-based design fee and missing cost details, the commission tabled a design contract with McKinley Architecture and approved allocating $668,524 in FY carryover levy funds to bring the animal-control project allocation to roughly $3 million.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
The Harrison County Commission tabled approval of a professional-services contract with McKinley Architecture & Engineering for the county’s planned animal-control facility and separately approved allocating $668,524 in carryover levy funds toward the project.
During a lengthy discussion, staff and commissioners described the contract as a professional services agreement that ties designer pay to an 8% fee of the anticipated construction cost. Staff said the contract used an anticipated construction budget of $4,000,000, which would make McKinley’s fee about $320,000 under the stated formula. Several commissioners objected that a percentage-based approach leaves the county exposed if construction bids deviate from the preliminary budget and asked if a fixed design fee or clearer cost breakdown could be substituted.
“Are you asking for us to impact with a fixed price for the design instead of a percentage?” one commissioner asked. Commissioners also noted missing line-item cost breakdowns and open design items — including sewer work and a generator — that should be included before committing to the agreement. Commissioners asked for additional detailed estimates, noting in-house estimating and third-party estimators produce different results.
Given those concerns, a commissioner moved to table the McKinley contract so staff could obtain clearer schematic cost breakdowns and address the open items; the motion carried by voice vote.
Separately, the commission voted to allocate $668,524 in last year’s levy carryover to the animal-control project, increasing the county’s committed funding toward a total allocation cited in the meeting of roughly $3,000,000. County staff said once the McKinley agreement is finalized they plan to issue RFPs for survey and environmental work and then proceed toward construction bidding.
The commission did not set a new deadline for bringing a revised McKinley agreement back but asked staff to return with the requested cost details.
AI generated
The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.
AI can make mistakes, so if you spot one, and we will fix it for everyone.
Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.

