Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the County Facilities topic
No spam. Unsubscribe anytime.
Benton County facilities update: crisis center slab, courthouse permits and EOC design progress
Summary
Facilities Director Gary Stockoff reported slab work at the crisis center, NEPA steps tied to HRSA funding, pending Corps of Engineers coordination for the courthouse, and continued design work for an Emergency Operations Center; budgets remain on track for current projects.
Get email alerts on the County Facilities topic
No spam. Unsubscribe anytime.
Gary Stockoff briefed the Board of Commissioners on several county capital projects.
He said the crisis center slab has been poured and walls will go up soon; county staff are finalizing NEPA work to access HRSA funding. On the courthouse project, Stockoff said the county has revised an MOU with the State Historic Preservation Office and is awaiting final Corps of Engineers sign‑off and city permits before construction can begin; he said bids are coming in and project costs have stabilized. Design development for the county’s Emergency Operations Center is underway, with construction expected to begin next year.
Stockoff also updated the board on the Monroe Clinic expansion planning and preliminary cost estimates and said the county would pursue the BP settlement reimbursement and continue NEPA and design steps before submitting grant materials.
Ending: He said the projects remain on schedule for late spring/early summer 2026 and that staff will return with next steps as permits and agreements are finalized.

