Atchison County approves ARPA road purchases, reviews culvert bid and authorizes public notice on obstructions
Summary
Commissioners approved ARPA-funded road purchase orders, heard a bid to replace a failing stone-arch culvert and authorized a county web notice on roadside obstructions; Road & Bridge superintendent Joe Snyder said the single bid was $74,775 and that pipe materials would be supplied by the county.
Get email alerts on the Road Infrastructure topic
No spam. Unsubscribe anytime.
The Atchison County Commission voted to approve several ARPA-funded road purchases and reviewed a bid to replace a failing arch culvert on 3 Fourteenth Road.
Road & Bridge Superintendent Joe Snyder reported that King’s Construction of Voskaloosa submitted the only bid to replace a failing stone-arch culvert; Snyder said the county would supply the pipe and that the contractor would handle installation, slope protection and seeding. "It's $74,775," Snyder said when presenting the bid. He told commissioners he would return next week with additional details and that the project is within $10,000 of his engineer estimate.
The board approved multiple ARPA purchase orders to fund recent paving and repairs: $12,433.78 to Superior Bowen (237.5 tons of asphalt), $32,526.73 to Leavenworth Asphalt Materials (two invoices) and $5,232.50 to Kansas Land Tire for specified tires. Each purchase-order motion was moved, seconded and approved by voice vote.
Separately, commissioners authorized the Road & Bridge superintendent to post county guidance on roadside obstructions to the Atchison County website as a public notice, a motion the board approved 3–0. Chair also noted that the county will distribute closure notices when culverts require short-term road closures and detours.
The board also approved a $250,730.50 ARPA purchase order to O'Keefe Wilson Abstracting Company to complete a property purchase intended as a future Road & Bridge facility; commissioners noted the closing is expected in December.
During public comment, resident Robert Grama asked for a status update on roadside culverts; officials said Road & Bridge would follow up and discuss the topic at the next meeting.
Next steps: Snyder will return with project-specific details, timelines and any required detours; county staff will post the obstructions guidance once wording is finalized.