Mingus Park community hall stabilization and restroom project face funding gap; city has earmarked capital funds

Coos Bay Parks Commission · November 21, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

City staff told the Parks Commission three grants and Adopt-a-Park fundraising have secured $45,331 toward a $99,402 foundation-stabilization project for the Mingus Park community hall; the restroom project is budgeted at $572,411 with a 40% match requirement and $395,964 secured to date, with remaining capital dollars identified if grants are not obtained.

A staff member reported to the Parks Commission on Nov. 21 that three grants—the Ford Family Foundation, the Coquille Community Tribal Fund and the Kinsman Foundation—plus $7,831 from Adopt-a-Park fundraising have yielded $45,331 toward foundation stabilization for the Mingus Park Community Hall.

"The total grants awarded plus the donated funds are $45,331 and the budget for this project is about $99,402," the staff member said. The staff presentation said the city will use $54,071 from the Parks Capital Fund if additional grant dollars are not secured; staff also warned that some grant awards (for example, from the Ford Family Foundation) have expiration timelines if not utilized.

Staff detailed the linked Mingus Park rewilding and restroom work. Rewilding elements include relocating playground equipment, enclosing a former picnic area and correcting drainage. The restroom project—presented as tied to rewilding funding—was listed with a total budget of $572,411 and a 40% match requirement. The staff report said $395,964 has been secured to date for the restroom project and that an additional $43,500 of capital funds may be used to complete rewilding work already started.

Commissioners asked about fund accounting and whether bike-and-ped and other project lines had been consolidated by the auditor; staff confirmed capital and bike-and-ped lines are tracked in city GL numbers (Fund 45 and Fund 2) and offered to make tracking clearer in future reports.

The presentation included programmatic next steps: staff is drafting request-for-quotes language for the foundation work (helical piers), will move forward on design and coordinate with the National Register process (staff said listing could unlock additional state historic preservation funding), and will continue applying for grants to avoid using capital reserves where possible.

The commission accepted the update; no formal vote was recorded.