Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Front St Mingus Bike Project topic

No spam. Unsubscribe anytime.

Coos Bay work session advances final design for Front Street–Mingus Park bike route amid ODOT crossing and parking concerns

Coos Bay City Council and Parks Commission (joint session) · September 24, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Staff outlined a preferred Front Street–Mingus Park bike route that would remove on-street parking on a three-block stretch on Commercial Avenue, require a new bike signal at Fourth & Commercial and an ODOT-approved crossing of Highway 101 (staff estimated roughly $230,000 for the crossing); council asked staff to advance final design and to seek a formal meeting with ODOT.

City staff presented a preferred alternative for a Front Street–to–Mingus Park bicycle route and asked the joint council and Parks Commission to advance the project into a final design phase.

The proposed route begins at Front Street and Market, crosses Highway 101, uses sharrows on Market to North Fourth Street, then travels west on Commercial Avenue into a two-way buffered bike lane on North Seventh Street between Fourth and Seventh, and concludes at the Mingus Park entrance. The plan includes a mirrored return route. "The preferred alternative included a return route with 3 blocks of a dual, 2-directional buffered bike lane on Commercial between Seventh and Fourth," said Eric Clough, a former Parks Commission member who commented during public comment and worked with the bike committee.

Staff said the route would remove on-street parking on the north side of Commercial Avenue between Fourth and Seventh — limited to that three-block stretch — and noted that many downtown businesses have off-street parking. "So there will be some loss of parking along that 3 block stretch," Clough said during public comment; "Nowhere else in town is there any parking being lost, being proposed."

Design challenges highlighted by staff include safe crossings of Highway 101 and a new bike-signal phase at Fourth and Commercial that may require a new pole. Greg, a city staff presenter, gave preliminary cost figures: an ODOT-required crossing could cost "right around $230,000," and the final-design work includes a $38,000 design budget staff recommended advancing to obtain more precise construction estimates. "It would require a new pole," Greg said about the Fourth & Commercial signal, but he declined to speculate on construction costs until a design phase provides firm numbers.

Councilors and commissioners said ODOT approval is a critical gating issue. "They will not and have not agreed to allow us even to put [a light] in," said Joe (no last name provided), a council member, describing past ODOT resistance to adding signals on that stretch of Highway 101; he urged staff to request a formal sit-down meeting with ODOT so the city can determine whether the crossing and signal are feasible. Several councilors suggested staff pursue a meeting with ODOT and pursue grant or match funding for both design and construction.

Next steps the joint group endorsed included advancing the route to a final design to produce firm cost estimates, preparing a budget request for the design phase, and coordinating a formal meeting with ODOT to resolve crossing permissions and constraints. If the final design confirms costs and regulatory feasibility, council will consider funding the construction phase in a future budget or grant application.