Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Facility Maintenance topic
No spam. Unsubscribe anytime.
District staff warn Mary Herbert Education Center needs major structural work; costs uncertain
Summary
District maintenance staff told the board that prior measurements show the Mary Herbert Education Center has settled several inches and support columns are shorter than designed; staff estimate stopping further movement could cost roughly $250,000 now but full remediation could exceed $1 million and won’t be known until walls are opened and engineering analysis is completed.
Get email alerts on the Facility Maintenance topic
No spam. Unsubscribe anytime.
Corey Nicollet, director of grounds and maintenance, updated the Emporia Board of Education on structural issues at the Mary Herbert Education Center.
Nicollet summarized KC Pro measurements taken 12/20/2023 showing settlement of roughly 3 to 3.75 inches in the southwest corner and described interior columns that are "not to the depth that they should have been," leaving the building with persistent structural limitations. He said contractors previously estimated $160,000–$190,000 to arrest visible movement and about $30,000 for exterior aesthetic work; Nicollet reported material and labor increases of about 10–15% since those figures and said the cost to arrest the condition could now be just under $250,000. He added that those figures would be a bandage rather than a full remedy and cautioned that complete repairs could be substantially higher — "I don't see how we end up under a million for any of this, potentially much more than that," he said.
Nicollet said KC Pro will remeasure the site and that the district will likely bring in a separate engineering firm for a more complete assessment, which historically has started around $20,000 for initial consulting. He emphasized that precise costs cannot be determined until walls are removed and the underlying condition is documented; staff expect a written report within approximately one week and said they will return to the board with specific recommendations after that analysis.

