ND PSC approves consent agreements: penalties for excavation violations and service-area certificate for MDU

North Dakota Public Service Commission ยท December 4, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

At its Dec. 4 special meeting the North Dakota Public Service Commission approved consent agreements in damage prevention enforcement cases assessing penalties for excavation violations (Capital City Construction and Arrow) and approved a joint service-area agreement for Montana Dakota Utilities and Chem Electric Cooperative in Lake Isabel near Dawson (PUD-24-324, PUD-24-325).

The North Dakota Public Service Commission approved several consent items by voice vote at its Dec. 4 special meeting.

Capital City Construction Incorporated (case DMD-24-23O): Speaker 2 summarized a June 10 complaint from CenturyLink alleging Capital City Construction excavated outside marked areas while repairing a parking lot in Mandan, removing a pedestal and disrupting CenturyLink circuits. The commission adopted a consent agreement finding a violation. The agreement assesses a $1,500 civil penalty with $750 suspended on condition of no further violations for five years; $750 is payable to the commission within 10 business days per the consent agreement.

Errol Rauschbout Services Incorporated / Arrow (case DMD-24-233): Speaker 2 moved to adopt a consent agreement arising from a June 13 complaint by North Dakota pipeline company Enbridge alleging a failure to contact the one-call notification center before excavation. Speaker 2 said Arrow admitted there was no evidence of contacting the one-call center prior to digging. The commission adopted a consent agreement assessing a $500 civil penalty with $200 suspended; Arrow is to remit $300 to the commission within 10 business days on the condition of no further one-call violations in five years.

Montana Dakota Utilities Company and Chem Electric Cooperative (cases PUD-24-324 and PUD-24-325): Speaker 2 said MDU and Chem filed a joint application on Aug. 20, 2024, for a consolidated service-area agreement in the Lake Isabel area near Dawson, North Dakota. The commission received no public responses, reviewed a jointly submitted map, and found the agreement avoids unreasonable duplication of service. The commission issued a certificate of public convenience and necessity to MDU authorizing service in the Lake Isabel area.

All three items were moved, seconded and approved by voice vote. Speaker 1 clarified the company referenced in the first consent item is Capital City Construction Incorporated (not Capital Electric Cooperative or the state capital).