Bond proposes operations at 22 North Maple; committee sends special-permit draft out with 24 conditions
Summary
Bond'represented petition for continued industrial/commercial operations at 22 North Maple Street was presented with a detailed conditions package covering enclosure, rodent control, truck routing, storage containers limited to jobsite 'gang boxes', hours of operation (5:00 AM'6:00 PM Monday'Friday) and environmental controls. Committee voted to forward the petition with 24 conditions and asked for a finding that storage-box approval is not precedent-setting.
Get email alerts on the 22 North Maple topic
No spam. Unsubscribe anytime.
The Special Permits Committee reviewed Bond's petition for the property at 22 North Maple Street and agreed to forward the application to action with a 24-condition package addressing operations, storage and truck routing.
Attorney Tarvey and Bond representatives (Paul James, Michael Moore and Tim Williams) outlined a plan that includes administrative offices, a training center, enclosures for outside storage, overnight parking for company vehicles and limited on-site storage containers used as jobsite 'gang boxes.' The petitioner reduced its initial request for containers and proposed an eight-container limit with a use pattern described as temporary staging for tools and equipment that are deployed to job sites and not permanently stored on-site.
Conditions proposed and discussed at the hearing included rodent-control measures before site disturbance with monthly reporting, a required snow-storage plan, chain-link fencing with privacy strips for outside storage areas, signage directing construction trucks to use the New Boston Street curb cut rather than Merrimack Street, granite curbing at the New Boston Street entrance, and a requirement to mechanically sweep any tracked debris from the street.
On operational hours the petitioner proposed standard hours (Monday'Friday, 5:00 AM'6:00 PM) with exceptions only for emergencies; the committee did not take exception to these hours for the industrial site format described.
Committee members asked for a formal finding at the public hearing that the permissive use of temporary jobsite gang boxes in this instance should not be precedent-setting for other properties. The petitioner and sponsor agreed to that approach and the committee voted to send the petition out to pass with the 24 proposed conditions.
Next steps: the petition will move to a public hearing with the amended conditions; committee staff and the petitioner will prepare the record language specifying the non-precedent finding for temporary jobsite containers.
(Representative quote) Attorney Tarvey summarized the approach: "These jobsite gang boxes would be filled with tools and mechanicals that would go on to a job... and they'll stay on that job, used on that job, and then when that job was done, it would come back."