Commission approves $100,000 contingency from ARPA for Trey Park playground project

Public Works Meetings · June 13, 2023
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Commissioners approved holding a $100,000 contingency in ARPA for the Trey Park playground project after staff warned general-contractor costs could exceed line-item allowances; the Cunningham Recreation equipment/installation quote and Kimley Horn engineering fees were discussed in detail.

The Public Works commission voted to hold a $100,000 contingency in American Rescue Plan Act (ARPA) funds to cover potential shortfalls on the Trey Park playground project. Staff presented a budget breakdown and warned the project could need additional contractor funds beyond current line items.

Speaker 6 said the Kimley Horn scope included $10,000 for grant administration and roughly $88,000 for engineering, and that Cunningham Recreation’s equipment-and-installation quote came in at about $1,050,000. Speaker 6 said there was approximately $31,500 remaining in engineering that could be moved to the general-contractor line, but that the $20,000 left for a general contractor in the current equipment/installation line was likely insufficient. "I just really wanna make sure that this project is done correctly, especially for the community," Speaker 6 said.

Commissioners debated options for reallocating engineering dollars and whether to formally transfer funds now. To avoid delays or shortfalls, a motion was made and seconded to place $100,000 in ARPA as a contingency and keep it in ARPA until needed. After a voice vote, Speaker 1 announced the motion carried.

The staff presentation included figures stated during the meeting: an engineering budget line about $88,500, $31,500 remaining in engineering services that could be reallocated, and a Cunningham quote discussed at $1,050,000 (project totals were discussed in the $1,050,000–$1,070,000 range). Staff indicated the project start date will likely be in July and said contractors expect the work "to be finished by next spring." The commission did not adopt a formal reallocation ordinance at the meeting; the contingency was approved by motion and will remain in ARPA until drawn upon.

What’s next: staff will finalize contracts and, if necessary, move budget lines or bring a formal fund-transfer request to the commission as the project nears construction.