Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Budget And Capital Projects topic
No spam. Unsubscribe anytime.
Board hears capital project timelines and 2025-26 budget outlook; middle school renovation estimated at $34.1 million
Summary
Finance committee reports outlined capital project status for a phase of school bond-funded work including a middle school renovation estimated at about $34.1 million, an expected construction start in Feb. 2025, and a 2025-26 budget timeline tied to an Act 1 index projected at 4%. The board received an unmodified audit opinion for 2023-24.
Get email alerts on the Budget And Capital Projects topic
No spam. Unsubscribe anytime.
Board members received detailed financial updates during the Nov. 19 meeting that covered capital projects, debt plans and the district's budget timetable for 2025-26.
A finance committee presenter summarized items from the Oct. 24 committee meeting, listing projects included in the current bond phase: a partial roof replacement at the high school (phase 3), middle school track and field renovations (phase 1 complete), an Erdenheim ramp with an expected two-week completion window, and the middle school renovation/addition whose design phase is complete. The presenter said construction for the middle school addition is expected to begin in February 2025 with an anticipated calendar-year-2026 completion and estimated the project cost at around $34,100,000.
The presenter described the district's borrowing history and plans: the district issued bank-qualified notes in 2023 and 2024 and expects to issue an additional $20,000,000 in 2025 and 2026 to complete capital projects.
At a subsequent finance report the board was told the 2023-24 audit resulted in an "unmodified clean opinion" with no audit findings. Revenues in 2023-24 were reported approximately $2,000,000 higher than budgeted due largely to investment earnings; the district's final fund-balance figure was reported in the meeting remarks (see clarifying details). The report also noted $1,460,000 in special losses tied to Carson Valley for 2022-24.
On budget guidance for 2025-26, presenters said the Act 1 index is projected at 4%, which the district estimated could yield roughly $2,000,000 in additional revenue. Known expenditure pressures cited included year-three of the STEA contract, debt service related to phase 3 borrowing, and projected medical and prescription cost increases of 11'12%.
Superintendent and finance presenters framed the Act 1 discussion as preparatory: approving an accelerated budget opt-out resolution (considered later in the meeting) would give the district more time to prepare a final budget to bring back for approval in the spring. The board was reminded the final 2025-26 budget is scheduled for approval on June 3, 2025.
The board did not take new borrowing actions at the meeting; the finance reports were informational and framed the timeline and cost assumptions for forthcoming bond-related activity.

