Weslaco approves UV modules, sludge pump purchase and seeks TWDB planning funds for South wastewater plant
Summary
The commission authorized a sole‑source purchase of UV modules (≤ $306,000), approved a sludge pump purchase (≤ $300,750), authorized solicitation of installation bids, and voted to apply to the Texas Water Development Board for up to $3.5 million in planning and design funding for the South wastewater treatment plant expansion.
Get email alerts on the Wastewater Infrastructure topic
No spam. Unsubscribe anytime.
Weslaco commissioners on Dec. 17 moved forward on a series of measures aimed at keeping the South wastewater treatment plant compliant and shovel‑ready for a larger rehabilitation effort.
The commission approved a sole‑source purchase of four ultraviolet (UV) disinfection modules from the plant's original vendor (Veolia/AquaRay) for a not‑to‑exceed cost of $306,000. Staff said the modules are compatible with the existing channel design and will help meet discharge and permitting requirements. "This is a compliance‑type purchase," a utilities official said; commissioners discussed the vendor's proprietary design and the need to avoid costly retrofits.
Commissioners also approved a purchase of a CPIC sludge pump for the water treatment plant from Dynamic Pump Systems under existing contract 672‑22 in an amount not to exceed $300,750. Utilities staff said the new pump replaces a single remaining pump so the plant will have a redundant pair for dewatering operations.
The commission authorized staff to solicit bids for installation labor for the UV modules; staff and commissioners noted the purchase of separate transformers and competitive quotes for that work will be brought back as additional agenda items.
Separately, the commission approved a resolution authorizing the mayor to file a funding application with the Texas Water Development Board (TWDB) for planning, acquisition and design (PAD) of South WWTP improvements, requesting up to $3.5 million to develop designs to make the project "shovel ready" for later construction funding rounds. Staff said the long‑term plan envisions increasing capacity by roughly 2 MGD beyond the project's baseline plan. "If we get funded for PAD, we'll be shovel ready when construction funding becomes available," a consultant said.
All items passed on voice votes; the record shows commissioners asking for additional documentation on transformer quotes and installation scopes before returning with a procurement recommendation.