Beatrice Public Schools reports steady progress on new PK–5 building; board tour planned Feb. 26

Beatrice Public Schools Board of Education · January 26, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

District staff told the board the new PK–5 building is largely drywalled, paint first coats are in place, 75% of mechanical/electrical/plumbing rough-in is complete, cabinets are arriving, and renderings and a board tour are planned; a cornerstone ceremony is scheduled for July 27.

District staff gave the Beatrice Public Schools board a construction update on the new PK–5 elementary building, reporting steady progress and near-term dates for review and celebration. Staff said work crews have largely completed drywall and first coats of paint in classrooms and preschool spaces, and that roughly 75% of mechanical, electrical and plumbing rough‑in is finished, inching the project toward installation of the electrical panel. Level 2 cabinets are being installed and Level 1 cabinets are due to arrive Feb. 15, staff said. Renderings of every room will be produced after furniture vendor School Specialty completes cross-references and design work; staff said those renderings will be presented to the board when available. Staff also said the district will schedule a board tour for Feb. 26 and may invite members of the ESU board to join. A cornerstone ceremony is planned for July 27 at 1 p.m.; district staff said local and state Masons are expected to attend and the public will be invited for limited viewing of the cornerstone inside the commons area.