Owner of 317 North Hogan reports cleanup, scheduled for Oct. 17 review
Summary
The property owner at 317 North Hogan told hearing officials he has cleared debris, is installing egress-compliant windows and will add a sump pump; the case was continued for a review on Oct. 17 with staff advising permits remain current.
Get email alerts on the Property Repair 317 North Hogan topic
No spam. Unsubscribe anytime.
An owner appearing at a public hearing reported tangible progress on repairs to a house at 317 North Hogan and agreed to a follow-up review on Oct. 17. Unidentified Speaker 2, the property owner, said he has "cleaned up the yard totally now," removed rubbish from the backyard and is preparing to install three remaining windows that he said will meet the 5.7-square-foot egress requirement.
The owner told hearing officials he has framed windows and will "put the windows in and dry it in" once remaining frames are completed. He also named contractors: "My new electrician is Matt from ... Next Level Electric Incorporated," and said "Alvin's the plumber on the job." Staff confirmed a plumbing permit was on file and that the electrician can be added to the permit by the owner.
Officials confirmed that typical building permits remain valid for six months as long as work continues. Staff advised that additions or structural changes require a permit; the owner said part of a previous porch structure had been removed and that he will obtain the necessary permits.
The owner and staff discussed a water-filled cellar on the property. The owner said he plans to pump it out, install a sump pump with a float, seal the cellar entrance and trench around cracked areas to redirect water. Staff noted the city will not remove a tree that stands on private property even if branches overhang a 10-foot utility easement; the owner said he will pursue removal and asked about city assistance for portions that overhang the easement.
The hearing body set a follow-up review for Oct. 17 and asked the owner to ensure electrical and plumbing work is permitted and the cellar entrance is sealed before that date. No formal vote was recorded; the continuance was scheduled by staff direction during the hearing.
The case will return for review on Oct. 17; the owner said he expects to renew permits if the work is not complete within six months.