Claremore council approves $2.122 million base bid for multi-year street-repair package
Summary
Council awarded the FY 2023–24 street repairs contract to Bridal Construction for a $2,122,000 base bid plus alternates, combining two fiscal years of maintenance work and prioritizing Northeast Street, parts of Cherokee and the Westwood subdivision.
Get email alerts on the Infrastructure Streets topic
No spam. Unsubscribe anytime.
The Claremore City Council approved a construction contract for fiscal-year 2023–24 street repairs, awarding the base bid of $2,122,000 plus alternates to Bridal Construction as presented by city staff.
City staff explained the package combines work that was delayed from the previous year's asphalt mill-and-overlay schedule and the current year's pavement-maintenance funds; treating the work as a single, larger project produced better unit prices, the staff member said. The presentation described the project area as primarily Northeast Street (north of the Will Rogers area), portions of Cherokee and sections of the Westwood subdivision. Staff noted the city has a five-year pavement-maintenance plan that prioritizes streets by condition and traffic volume.
Council members asked whether the contractor had performed work for the city previously; staff said the bidders had performed work on prior projects without issue. The contract includes concrete panel replacements when needed and fixes to the road substrate in problem areas. The motion to award the contract was made, seconded and approved by roll call.
Staff said the city's pavement-maintenance spending over recent years (including this packaged project) totals several million dollars; the council approved the recommendation to proceed.