City opens final storm-recovery RFPs, seeks permanent debris-removal consultant
Summary
City staff said it opened the final RFPs for storm recovery, including a permanent debris-removal contract and a permanent consultant RFP required by FEMA; the manager estimated about 500,000 cubic yards were already collected in initial response work.
Get email alerts on the Storm Recovery topic
No spam. Unsubscribe anytime.
The Fenimore City manager reported that the city opened the final two request-for-proposals related to storm recovery, including a permanent RFP for debris and vegetation removal and an RFP to select a permanent consultant for recovery oversight.
The manager said the city had previously issued an RFP for temporary utility debris work and had picked up roughly "500,000 cubic yards, if not more" during the initial response. He said the permanent removal and consulting contracts will require several weeks to months of work and multiple passes through the city to complete the effort.
City staff explained that debris from yards (vegetation, fences, sheds separated from vegetation) will be processed differently and that loads will be documented and taken to appropriate waste facilities; costs for processing construction debris were described as dependent on the receiving facility.
The manager said FEMA requires issuing an RFP for a permanent consultant even though the city had already hired a consultant for the initial 90-day response. A committee reviewed proposals and will verify documentation, then notify unsuccessful bidders.
Next steps: staff will finalize RFP details, notify bidders, award contracts and begin multi-pass removal and disposal operations as contracts are executed.
No vote was recorded on this informational report; it was presented as a staff update.