Mount Vernon officials approve City Hall roof payment, say broader building repairs exceed $200M

December 27, 2024 | Mount Vernon, Westchester County, New York


This article was created by AI summarizing key points discussed. AI makes mistakes, so for full details and context, please refer to the video of the full meeting. Please report any errors so we can fix them. Report an error »

Mount Vernon officials approve City Hall roof payment, say broader building repairs exceed $200M
The Board of Estimate and Contract on Dec. 27 approved a change order and final payment to Weathertight Systems Inc. for additional repairs to the City Hall roof, but officials said the work represents only part of a much larger backlog of capital repairs across municipal facilities.

During discussion the city’s project staff said the current work addressed multiple roof sections and flashing, but additional envelope repairs — including parapet work and brick pointing around windows — still require funding. The board was told that some envelope items remain unfunded even as repairs to the main roofing elements were completed. Officials estimated capital repairs across city buildings exceed $200 million and listed major projects including an estimated $13 million need for police and court building roofs and roughly $6 million for fire department projects.

Members pressed staff on funding sources and sequencing. Staff said ARPA funds are being used for the City Hall repairs and that the city has also identified state and federal funding streams — including DEC/EFC grants and a state water infrastructure program — and a $5 million revolving loan fund that can be used to smooth cash flows pending reimbursements. The board directed DPW and the Comptroller to set up separate accounting so reimbursements are tracked and do not commingle with the general fund.

Officials said engineering and condition reports are near final and will include estimated costs to support future capital planning and grant applications. The board approved the final payment on roll call with no recorded opposition.

Next steps: DPW will finalize and submit prioritized cost estimates and the Comptroller’s office will confirm account separation for grant reimbursements and report back to the board.

Don't Miss a Word: See the Full Meeting!

Go beyond summaries. Unlock every video, transcript, and key insight with a Founder Membership.

Get instant access to full meeting videos
Search and clip any phrase from complete transcripts
Receive AI-powered summaries & custom alerts
Enjoy lifetime, unrestricted access to government data
Access Full Meeting

30-day money-back guarantee

Sponsors

Proudly supported by sponsors who keep New York articles free in 2026

Scribe from Workplace AI
Scribe from Workplace AI