Board accepts facilities report; sprinkler testing, roofing and playground projects to continue
Summary
The board accepted the facilities report, which included final acceptance for some completed projects and updates on ongoing work: sample sprinkler-head testing at several sites, PVC reroofing about 85% complete at the district office, a compressor replacement planned for a dry‑sprinkler system, and a playground project with permit in hand and anticipated late‑January start.
Get email alerts on the Facilities topic
No spam. Unsubscribe anytime.
The board accepted the facilities report at the Dec. 19 meeting and heard updates on several building and maintenance projects.
Completed work seeking final acceptance included a reroute project at the high school and work in the auto shop. Facilities staff described sample sprinkler‑head removals scheduled for testing (sample sites include Mill Pond and select gymnasiums), and said technicians will take a few heads for inspection to ensure systems function correctly.
Staff noted a planned replacement of a compressor for the dry‑sprinkler system near the gym/server area because the existing unit has reached the end of its useful life; scheduling for that work will appear on a future facilities update. The district reported the PVC reroof at the district office is about 85% complete, with finishing metal work remaining.
A playground project (Southworth) has its permit in hand and staff expect to meet with the contractor to finalize a schedule with a likely late‑January or early‑February start, weather permitting. A small fencing project and bioswale adjustments at the bus loop were also discussed.
Board members asked about documentation and photos for future updates; facilities staff said they can provide visual materials at subsequent meetings.