Twin Towers construction: board hears progress report; contractors warn of long-lead equipment and propose night shifts to limit disruption
Summary
KD&G and Triton representatives updated the Middletown Board on the Twin Towers project progress (excavation, foundations, asbestos abatement and window replacement), warned of long-lead electrical equipment (about 13 months to procure) and described night-shift scheduling and containment measures to limit classroom disruption.
Contractors for the Twin Towers renovation told the Middletown Board of Education on Oct. 24 that foundation work, utility relocations and asbestos abatement were completed over the summer and that structural work will be visible in coming months.
KD&G and Triton representatives described the project phasing: Phase 1A includes a multi-story classroom addition and renovations; Phase 1B covers the new cafeteria and food-service areas. Presenters said excavation and foundation walls are in place and that site work, rebar and concrete preparation are ongoing. A…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat