Facilities staff defend energy‑performance work, seek two HVAC technicians as new chillers arrive
Summary
Facilities staff described an ongoing energy‑performance contract tied to a debt instrument and asked for two dedicated HVAC technicians who they said would reduce vendor diagnostic costs and better maintain the county's chilled‑water systems as new chillers are installed.
Get email alerts on the Facilities topic
No spam. Unsubscribe anytime.
Facilities staff and the county’s mechanical engineer explained the county’s energy‑performance work and asked commissioners to support adding two dedicated HVAC technicians.
The contract with a vendor (Johnson Controls/JCI) implements BACnet monitoring across major courthouse and jail HVAC systems, they said, and is tied to a bond or third‑party financing arrangement that requires performance verification through roughly 2029. Facilities staff said phase 1 of the retrofit produced measurable kilowatt‑hour reductions; the bond repayment schedule directs a portion of savings to debt service. The county also reported some contract credits in recent quarters when guaranteed savings targets were not met.
Facilities staff requested two technicians dedicated to HVAC controls and chilled‑water systems; they estimated that in‑house expertise would cut vendor diagnostic and call‑out costs and speed repairs. "By having these two people on board, they would be able to fix smaller issues…you'd still come out saving about $100,000 a year," the facility engineer said, while acknowledging some savings are applied to debt service tied to the original project.
Commissioners asked procurement and facilities to present a third‑party verification evaluation at the next court meeting and requested a clear ledger of energy savings, debt payments and net operating impact to assess contract value as new chillers are installed.
What happens next: Staff will present a third‑party verification report and a spreadsheet showing baseline, verified energy savings, debt obligations and net fiscal impact; commissioners asked for a plan to align vendor contracts with equipment lifecycles.