Comite diversion update: most parcels acquired but Florida Gas relocation and Brooks Lake appraisal remain unresolved

Amite River Basin Drainage and Water Conservation District · December 10, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

ARBC legal counsel reported that 85 of 89 parcels for the Comite River diversion have been acquired and highway/bridge work is largely underway, but the status of Brooks Lake appraisal and whether Florida Gas must be relocated (which could trigger FERC review) remain open and could affect timeline.

ARBC legal counsel told the board Dec. 10 that 85 of 89 parcels for the Comite River diversion project have been acquired and that related highway and bridge work is progressing (Highway 964 about 91% complete; Highway 67 about 89.5% complete). Counsel and staff noted outstanding items including an appraisal for Brooks Lake and utility relocation complications.

Board members raised concerns about Florida Gas, which is sited near the proposed Brooks Lake alignment. Counsel said the U.S. Army Corps of Engineers is examining whether the pipeline relocation can be avoided; if relocation is required it could trigger a Federal Energy Regulatory Commission (FERC) process and add cost and time.

Larry Marino (project staff) said Florida Gas has mobilized and begun preparatory work, but the timeline will depend on the Corps’ review and any required agreements with the pipeline operator. Commissioners asked whether the Corps or its regional representative could be invited to the next ARBC meeting to provide an update; the board did not take a formal vote but supported outreach.

Next steps: staff will track outstanding appraisals and utility relocation analysis and consider inviting Corps representatives to a future meeting to clarify schedule and permitting requirements.