Board approves several public-works payments, tables one purchase order

Board of Aldermen · November 15, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The board approved a Spencer contracting change order and contractor payments for the Pacific lift station and the Highway N project, and tabled a $64,500 purchase order to Kirby Smith Machinery pending budget review.

The Board of Aldermen on Nov. 15 approved a set of public-works items and delayed others pending the Nov. 19 budget review. The board voted to approve a $19,030 change order for Spencer Contracting for the 2024 asphalt overlay and sidewalk improvements and approved pay applications for ongoing projects.

Specifically, the board approved pay application #10 from KJU for the Pacific Lift Station project in the amount of $80,302.85 and payout #3 from KJ Understahl for the Highway N project in the amount of $401,046.94. Public-works staff said final paving on the Highway N project is anticipated on Tuesday, after weather-related delays, and that the road will remain single-lane while ancillary work (dirt, sidewalks, yard restoration) continues.

The board also considered a purchase order from Kirby Smith Machinery for an air burner totaling $64,500. After questions about quarterly budget status, a board member moved to table that purchase order until the Nov. 19 meeting and the motion carried. The board agreed to prioritize items that were time-sensitive (the asphalt overlay and highway payouts) and to defer lower-priority expenditures to the next meeting for additional budget review.

Separately, public works reported final bulk-trash pickup removed 41.54 tons at a total cost of $12,887.60. Staff also said they would add Ben Ridge Estates / Winter Meet Trail to the city's speed-limit schedule as 25 mph and asked the city attorney to draft the necessary ordinance language so signage and enforcement can proceed.

Next steps: staff will proceed with contractor payments and schedule remaining purchase approvals for Nov. 19, and will notify contractors of paving schedules.