The Milton School Committee reported it has been invited into the Massachusetts School Building Authority process, voted to recommend a $1.5 million appropriation for a feasibility study and to add several ex officio, nonvoting positions to the school building committee to align with MSBA rules.
Get email alerts on the School Building topic
No spam. Unsubscribe anytime.
Milton Public Schools has been formally invited into the Massachusetts School Building Authority (MSBA) program, the district announced at the Dec. 18 School Committee meeting — a development that launches a multi-year planning and construction cadence for addressing school space needs.
Staff said the MSBA process involves multiple modules and that the district is in the eligibility phase; Module 1 (a 270-day eligibility period) is expected to begin May 1. The MSBA staff described a typical 5–7 year timeline from eligibility to project completion, though committee members said prior work could shorten the schedule.
To prepare, the school building committee recommended two warrant articles for the town’s February meeting. One article would ask the town to appropriate $1,500,000 to pay for the feasibility study and schematic design work required to join the MSBA schedule; the owner’s project manager provided the estimate to cover the schematic-design phase. The school committee voted to recommend that appropriation be placed before town meeting, and the Chair said funds would be expended under the direction of the school building committee if approved.
A second warrant article would amend the school building committee roster to add several ex officio, nonvoting positions required under MSBA practice: the superintendent, the town administrator, the director of consolidated facilities, an MCPPO-certified representative appointed by the school committee, a school principal appointed by the school committee, and a local town budget official. Committee members said adding these ex officio members would allow staff to participate fully in design conversations while keeping the SBC’s appointed voting membership intact.
Committee members discussed financing options: the $1.5 million feasibility ask is expected to be funded through the town’s normal debt service and would not require a Proposition 2½ override. Members noted that the appropriation could affect the town’s capital program and agreed capital-planning staff would examine trade-offs.
Next steps: if town meeting approves the funding, the district will proceed with MSBA-required submittals and begin Module 1 work on or after May 1; the SBC and central office will also implement the roster changes if the warrant article is adopted by voters.