Putnam County officials report progress on ARPA‑funded Stabilization Center but lease and planning approvals still pending
Loading...
Summary
Social Services Commissioner Sarah Servideo told the county committee that a contract is executed and ARPA funds are encumbered for a planned Stabilization Center; staff said a lease is pending, the director is hired, and a Carmel planning‑board submission is expected after engineer calculations, with contingency options under consideration.
Putnam County Social Services Commissioner Sarah Servideo told the Health, Social, Educational & Environmental Committee on Nov. 21 that the county’s planned Stabilization Center has moved forward in recent weeks: necessary health‑department approvals and a septic permit have been received, a contract was fully executed, and ARPA funds for the project have been encumbered for ARPA purposes. "The contract was fully executed today. All signatures were obtained today," Servideo said.
Servideo and county staff said People USA, the organization contracted to operate the center, has been recruiting staff aggressively; the center’s director has been hired and will also help launch a mobile crisis team. Staff described outstanding tasks: finalizing a lease with a landlord (staff said an existing tenant is in the process of eviction) and completing engineering calculations for the Carmel planning board submission. Committee members were told the planning‑board package is likely to be ready in the early months of the new year if it cannot be placed on the Dec. 12 agenda.
Committee members pressed staff about contingency options if the Carmel planning board does not approve the current site. Staff said county leaders have discussed alternative locations and non‑brick‑and‑mortar models as fallbacks, but cautioned such alternatives would require additional policy work and possibly new approvals. One legislator asked whether ARPA funding would be jeopardized if the site or project scope changed; staff advised that legal and ARPA‑committee follow‑up would be needed to confirm eligibility.
Several legislators emphasized the project’s urgency and the importance of completing outstanding items promptly. The committee did not take a formal vote on the Stabilization Center during the Nov. 21 meeting; the update was recorded for follow‑up and members requested memos and legal guidance on site contingency and ARPA compliance.
Next steps outlined in the meeting record included: confirming lease execution, obtaining final engineering calculations for the planning‑board submission, and follow‑up with the ARPA committee or legal department to verify continued eligibility should project details change.

