Public Works reports on signals, sinkhole repairs and FEMA-linked roof work
Summary
Public Works updated the committee on a range of infrastructure items: traffic signal testing scheduled for Nov. 12 pending county clearance, Lewis Avenue sinkhole repairs completed, and a city hall roof project delayed into November–December with a FEMA-related deadline in February 2025.
Get email alerts on the Public Works topic
No spam. Unsubscribe anytime.
City public works staff briefed the Brentwood Public Works Committee on ongoing infrastructure and maintenance projects, including traffic signal equipment, roadway repairs and FEMA-linked capital work.
Staff said signal equipment for an intersection had been shipped and county testing is scheduled for Nov. 12; if county testing succeeds, coordination with Union Pacific Railroad will follow. A curb design question at Collier and Russell drew resident preference for a 12-inch curb that mirrors a nearby strip mall; staff will confirm slope implications with the design team.
Public Works reported the Lewis Avenue sinkhole was caused by a failing lateral and a failing MSD trunk line; rehabilitation work addressed both issues and crews will finish with asphalt patching after concrete pours. A retaining wall between Hilldale and Manderly is leaning; staff have engaged a design-build consultant to provide a budget range so the city can scope an RFP for early-next-year work.
Staff also said the city hall roof replacement was pushed into November/December because of a regional shingle shortage; staff plan to do flat-roof work while awaiting shingles and noted a FEMA project deadline in February 2025 tied to related work.
No formal board action was required for the reported items; staff will return with contract and scheduling details as work progresses.