APC staff reports administrative TIP reallocations, Sagamore Parkway Trail funding and FY2025 obligations

MPO Policy Board · November 25, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

APC staff described three administrative TIP modifications (including reallocation to Bridge 527 and the Sagamore Parkway Trail), reported that obligated funds for Bridge 527 appear on the latest report while Morehouse Road obligations were delayed, and reviewed upcoming bid lettings.

APC staff reported several administrative adjustments and fund‑tracking updates at the Jan. 9 meeting.

Doug (APC staff) explained three minor TIP modifications: two parts of a Tippecanoe County project on old US‑231 near McCutcheon High School received reallocated federal funds assigned to construction engineering and construction (an 80/20 federal/local match), and a separate reallocation moved $171,063 in residual federal funds into two phases of the Sagamore Parkway Trail (construction engineering and preliminary engineering). He characterized these as administrative modifications that do not rise to full TIP amendments.

On the status of FY2025 federal funds, Doug said the most recent obligation report arrived from central office too late to include in meeting materials; it does show obligation for Bridge 527 but did not yet reflect the Morehouse Road project because of a delay in central‑office purchase order posting. Staff expect the Morehouse Road obligation to appear on the next report and said they are monitoring residual federal funds and have plans to allocate them.

Doug also walked through the 18‑month letting list, noting two state projects scheduled for the next INDOT bid letting (traffic signal visibility improvements and raised pavement marking refurbishing), the SR‑225 pavement rehabilitation pushed to a May letting because few contractors perform that work, and a South Ninth Street project listed for Jan. 14, 2026.

What’s next: staff will post updated TIP materials, include the administrative modifications in the next meeting summary, and report obligations in the next FY2025 funding update.