Architect lays out phased timeline for Hopewell Valley referendum projects, roofs and HVAC earliest priorities
Summary
District architect outlined a preliminary timeline after last month’s referendum: summer 2026 roofing at three schools, phased 2027 renovations including HVAC with long lead times (40+ weeks for major equipment), and public bidding and agency reviews to follow.
The board heard a detailed, preliminary timeline for capital projects approved by voters in the recent referendum.
Dan Scatone of the district’s architect firm (speaker 12) said immediate work will focus on design and engineering, public bidding and agency reviews. "The first round of roofing at these 3 schools — the high…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat