Parish engineers report progress on airport connector, pump stations and pump‑station change orders
Summary
Engineers told the Lafourche Parish Council that the airport connector and lift span are nearing assembly with a likely 3–4 day bayou closure for installation, several pump station projects are moving to bids or construction and the Moore Vaughn contract was adjusted with a $12,010 balancing change order.
Parish engineers updated the Lafourche Parish Council on Dec. 10 about multiple infrastructure projects, including the airport connector and lift bridge, two pump station projects and a change order on the Moore Vaughn pump station.
Joe Pisiola of Pisiola & Associates said Sea Level Construction is progressing on the airport connector road and the lift span: "They're doing some touch up welding and some touch up painting. And it'll be put on a barge and then rotated into place..." He warned that installing the lift span will likely require a 3‑ to 4‑day closure of…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat