Committee members questioned high utility invoices and small-purchase controls during a review of the monthly transparency report, highlighted a $7,016.12 water bill for Ladies Island Middle and a nearly $65,000 Dominion Energy bill for May River High, and reviewed larger contract payments including Ajax Building and Catapult Learning.
Get email alerts on the Transparency topic
No spam. Unsubscribe anytime.
During its Dec. 5 meeting the Beaufort County Board of Education Finance Committee reviewed the district's monthly transparency report and raised questions about high utility bills, small p-card purchases, and several large contracts.
Chair highlighted invoice 639 from Buford Jasper Water & Sewer for Ladies Island Middle School at $7,016.12 and asked operations staff to investigate the cause; staff said some schools experienced leaks and agreed to schedule an operations--finance meeting to answer the committee's questions.
The committee also discussed a Dominion Energy bill for May River High School billed at $64,986.64, significantly above other large schools. Operations staff said construction features and prior HVAC reviews are being examined and recommended a more rigorous energy review.
Small purchases drew scrutiny after the chair asked about a $9.98 p-card purchase at Saint Helena Elementary. Purchasing staff explained the p-card can be authorized for event-related purchases and may list multiple vendors for a single event to avoid repeated approvals; documentation and sign-in sheets are required to support refreshment purchases. The chair expressed concern about balancing accountability with staff workload: "I don't want to lose accountability," the chair said, adding the process must also be efficient.
Committee members reviewed larger payments in the consolidated report, including payments to Ajax Building Company totaling $369,256.94 and a Catapult Learning intervention contract at about $592,000. Staff said Catapult Learning services are funded through a mix of special revenue (ATSI/CSI), state EIA funding, and the general fund and that further funding details will be provided.
Finance staff also described a planned change to the district's timekeeping system: the district is implementing an Executime module from Tyler Technologies (replacement of Novatime) and expects kiosk and clock replacements over the winter with implementation by mid-to-late spring.
The committee voted unanimously to recommend OE 6.1'6.8 to the full board; that item will be placed on the next full board consent agenda.