Committee approves two change orders and task-order contracts for Low Battery Phase 4
Summary
The committee approved Change Orders 5 and 6 for the Low Battery Phase 4 CMAR contract—Change Order 5 for $423,411.80 (brick arch repair and paver support) and Change Order 6 for $548,783.91 (CWS utility relocation, reimbursable by CWS)—and also authorized multiple task-order contracts for arch rehabilitation.
The Public Works Utilities Committee approved two change orders to the construction manager‑at‑risk contract for the Low Battery Phase 4 project and authorized multiple task‑order procurement contracts to support arch rehabilitation across the peninsula.
Matt Fountain described Change Order 5 as totaling $423,411.80 and consisting of two primary elements: roughly $200,000 to repair a collapsed brick arch and stabilize…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat