County approves public‑works feasibility study and authorizes multiple ditch cleanouts totaling an estimated $225,000
Summary
The board authorized two owner’s‑representative agreements for a public‑works campus feasibility/master plan (budgeted at $75,000) and the Drainage Authority approved cleanouts for County Ditches 46A ($65,000 est.), 47A (cost not specified in transcript) and 78 ($160,000 est.), with staff explaining bidding/billing and stabilization limitations.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
Nicollet County commissioners approved agreements Aug. 27 to hire two owner’s‑representative firms to lead a public‑works campus feasibility and master‑planning phase and, under the Drainage Authority, authorized several ditch cleanouts with estimated combined costs reported in staff presentations.
Public‑works staff recommended two firms—CMCC and BRCC—as complementary owner’s representatives to assist with design‑team selection, site evaluation and project planning for a new public‑works campus. Staff said the study was budgeted in 2024 and 2025 with an adjusted placeholder of $75,000 to accommodate the planning phase and noted a BRCC contract clause limiting aggregate liability to fees paid for services; the board approved both agreements.
Shortly after, the board convened as the Drainage Authority and approved a contract with Tim and Mary Weibel for cleaning County Ditch 86A (Sept. 1, 2024–Dec. 31, 2025). The authority then considered three repair requests:
- County Ditch 46A: Ditch inspector Nate Henry recommended cleaning ~4.5 miles (plus ~0.5 miles staff added) to address sloughing and silt captured after heavy rains; estimated cost $65,000. No landowners objected; the authority approved the cleanout.
- County Ditch 47A: Inspector recommended cleaning ~3 miles on a very flat stretch where small silt deposits greatly affect flow. A landowner, Eric Anixton, asked how billing would be assigned. Public‑services staff (Jackie) explained billing flows to County Ditch 8 and benefited landowners (including Ditch 82) would receive proportional shares; the authority approved the cleanout.
- County Ditch 78: Inspector recommended cleaning ~11.5 miles including main lines and branches; estimated cost $160,000 for cleaning, leveling, tree removal and reseeding. Landowner Richard Galslick asked about steep vertical banks and options such as riprap; staff said full resloping would require taking additional land and that riprap or targeted stabilization may be employed where necessary. The authority approved the cleanout.
Board members characterized the public‑works feasibility study and ditch maintenance approvals as fiscally prudent steps toward long‑term infrastructure upkeep and safety. Staff flagged that the public‑works study was budgeted and would be paid from the public‑works budget.