The board set a Dec. 17 public hearing for the county's 2025–2029 CIP, adopted a MnDOT intersection lighting resolution and Agreement No. 1058283, and approved Right‑of‑Way Plat 33 and an acquisition resolution for State Aid project 52606007 (County Road 6/Kiner Road), including eminent‑domain authorization and compensation language.
Get email alerts on the Infrastructure Projects topic
No spam. Unsubscribe anytime.
Nicollet County commissioners on Nov. 12 set a public hearing for the county’s five‑year Capital Improvement Plan and approved multiple transportation actions, including a resolution and agreement with MnDOT for intersection lighting and a right‑of‑way acquisition package for a County Road 6 reconstruction project.
Finance staff asked the board to set a public hearing under Minnesota Statute 373.40 for the 2025–2029 Capital Improvement Plan; the board set the hearing for Tuesday, Dec. 17 at 9:15 a.m. The plan will identify estimated capital expenditures and funding sources for the five‑year period.
Public works staff presented a MnDOT intersection lighting resolution and Agreement No. 1058283; the board adopted the resolution by roll call and later approved the agreement unanimously.
Public works also sought approval of County Right‑of‑Way Plat 33 and a resolution authorizing acquisition of permanent right‑of‑way and temporary construction easements for State Aid project 52606007 (Kiner Road/County Road 6 realignment near North Mankato). Staff said the plat covers the corridor needed to realign a skewed intersection (409 Avenue) to a 90‑degree connection with County Road 6 and identified a small parcel to be acquired from Lowe’s Oil Company. Staff explained acquisition language includes eminent‑domain authorization only as a last resort and that acquisitions will include compensation; the county intends to deed the permanent right‑of‑way to the township after project closeout. The board approved Plat 33 and the acquisition resolution unanimously.
In a construction update on County Road 21 slope rehabilitation near New Ulm, public works said crews have placed about 31,000 tons of riprap — roughly 7,000 tons more than estimated — because of soft soils encountered; funds are available to cover overruns and staff said the embankment is now protected though some follow‑up work may continue depending on weather.
All transportation motions were adopted unanimously.
AI generated
The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.
AI can make mistakes, so if you spot one, and we will fix it for everyone.
Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.