District outlines CM/GC procurement path for middle school, schedules public hearing and RFP timeline

Molalla River School District Board (work session) · October 25, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

District consultants explained the construction manager/general contractor (CM/GC) delivery method, said Oregon Revised Statutes require findings of fact for an exemption from design-bid-build, and announced a Nov. 14 public hearing and mid-December RFP evaluation timeline.

Consultants for the Molalla River School District presented the construction manager/general contractor (CM/GC or CMGC) approach on Oct. 24, describing the selection steps, benefits and statutory requirements for using an alternative delivery method.

The consulting team said CM/GC selection emphasizes qualifications, bonding capacity and project approach over lowest-cost bids and includes a preconstruction services contract followed by a guaranteed maximum price (GMP) near about 75% of construction documents. "The district will issue a request for proposals to interested contractors... selection is largely based on qualifications," a presenter said, describing fee, preconstruction costs and general conditions that will be part of contractor proposals.

Because Oregon law favors design-bid-build, consultants said the board must adopt findings of fact to justify an exception; the team said a public hearing will be posted for the district's upcoming business meeting (Nov. 14). The presenters outlined next steps: post the RFP publicly, expect proposals in by mid-December for evaluation, interview shortlisted teams and then enter a design-phase contract with the selected CM/GC. The district also plans outreach to local subcontractors so smaller regional firms can compete for trade work.

Consultants explained risk and warranty handling: the project will carry standard warranties (one-year general warranty, longer warranties for specific components) and an 11-month walkthrough with architect and contractor to identify items the contractor must correct at no cost to the district.

Board members asked about differences between CM/GC and design-bid-build, the role of the district in selecting the architect and contractor, and the potential for local contractors to participate; the presenters answered and said the board will act as the local contract review board when it considers findings of fact.

No approval was requested tonight; consultants said the board will be asked to take action on the procurement process at a forthcoming business meeting after the required public hearing and findings of fact are posted.