Pension Solution project hits UAT milestones; payroll run succeeded, go-live still targeted for fall 2025

California State Teachers Retirement Board · November 7, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

CalSTRS reported progress on the Pension Solution project’s user-acceptance testing (UAT): more than 3,000 SIT scripts passed, 300+ UAT test scripts prepared, the first monthly payroll (415,000 recipients, ~$1.5B) ran in test successfully, and the fall 2025 go-live date remains the target with soft-launch and cutover plans.

CalSTRS project leaders updated trustees Nov. 7 on the Pension Solution program, the multi-year replacement of the benefits administration system. Anthony Sweeney, project director, said the project moved fully into user-acceptance testing: over 300 of roughly 440 UAT scenarios have been drafted and the team has executed more than 3,000 system-integration test scripts, closing most previously identified gaps.

Sweeney said defects exposed in system integration testing remain under active resolution; most types of defects have been identified as SIT execution has approached completion and the critical/high defect count has decreased. He asked the board to note that some UAT failures reflect tester training, data or technical-configuration issues and that nearly one-third of reported UAT issues are not true functionality defects.

A major milestone: the team executed a first monthly payroll run in the test environment that included 415,000 benefit recipients and approximately $1.5 billion in payments; the run completed smoothly and will serve as the basis for many downstream tests. Staff outlined a soft-launch window and pre-cutover/cutover/post-cutover schedule toward a fall 2025 go-live, and noted $129 million of remaining go-live budget with an additional $104 million approved for post-implementation stabilization and operations.