DEQ presentation flags common vapor intrusion pitfalls that delay occupancy
Summary
DEQ groundwater staff advised developers to follow VIMS guidance, provide full installation reports with pre-occupancy sampling and photos, and watch for common issues — missing or reversed fans, incomplete vent routing and confounding indoor sources — that can force resampling and delay occupancy.
Jordan, a groundwater professional presenting to Brownfields stakeholders, summarized common construction and sampling problems that delay occupancy of redevelopment projects and offered practical steps to reduce delays.
‘‘We really need a final installation report with pre-occupancy sampling in accordance with the VI matrix before we can give a green light to occupancy,’’ Jordan said, stressing that installation documentation and pre-occupancy field data are necessary for DEQ to…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat