ISG engineer: rail extension mostly complete; paving expected after weather delay
Le Mars City Council · November 19, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.
Summary
Ari Hoekstra of ISG told the council ballast and switches for the industrial-park rail extension are in place. Paving by contractor Halstein was delayed by rain and cold but is expected to begin by the end of the week, with most work aimed to finish before Thanksgiving.
Ari Hoekstra, civil engineer with ISG, briefed the council on progress for the rail extension into the industrial park, saying crews "got all the ballast put in, switches and all that stuff."…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat
30-day money-back on paid plans