ISG engineer: rail extension mostly complete; paving expected after weather delay

Le Mars City Council · November 19, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Ari Hoekstra of ISG told the council ballast and switches for the industrial-park rail extension are in place. Paving by contractor Halstein was delayed by rain and cold but is expected to begin by the end of the week, with most work aimed to finish before Thanksgiving.

Ari Hoekstra, civil engineer with ISG, briefed the council on progress for the rail extension into the industrial park, saying crews "got all the ballast put in, switches and all that stuff." Hoekstra said the contractor Halstein will perform paving across the rail crossing but weather delays (rain and colder temperatures) pushed the paving start toward the end of the week.

Hoekstra said the project team is "shooting for the end of this week to start" and that the goal is to have the majority of work finished before Thanksgiving. The update answered a council request for status and scheduling; no change orders, contract amounts or new funding sources were announced during the update.

Council members acknowledged the timing and thanked staff for the progress report.