Developer proposes 19-lot Brookside Farms Phase 2; board delays site walk because of weather

Town of Wells Planning Board · December 2, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Developer Jason Levante presented a pre-application for Brookside Farms Phase 2: 19 lots on a 51-acre site with five wetland crossings and about 8,600 sq ft of new wetland impact; DEP and Army Corps review will be required. The board received the pre-application and deferred scheduling a site walk due to snow.

Jason Levante, the developer, asked the Planning Board to receive a pre-application for Brookside Farms Phase 2, a single-family subdivision that would add 19 lots to an existing project.

Levante said the 51-acre proposal would retain roughly 59% open space, include five proposed wetland crossings (four for a road and one for a driveway) and rely on individual septic systems and wells. "What's proposed are 19 new lots," Levante said. He told the board the wetlands were delineated by Chris Kopi and noted a potential vernal pool that will be researched in spring.

Staff flagged regulatory reviews the project will need: Maine DEP site law major amendment review and an Army Corps wetland impact review. Levante provided impact figures: "A total of 8,600 square feet of new wetland impact is proposed," and he said the cumulative wetland impact with Phase 1 would be about 36,000 square feet.

Board members discussed scheduling a site walk and sidewalk review. Because snow cover and a forecast of further storms would make a site walk impractical, the board voted to receive the pre-application and defer setting a firm site-walk date. The board advised the applicant he could continue work on plan materials "at your own risk" while the sidewalk/site-walk is delayed.

Why it matters: The project will require state and federal review because of the wetland impacts identified by the applicant; the board and staff asked for vernal-pool confirmation, updated house footprints to reflect wetland setbacks and digital survey data for plan accuracy.

Next steps: The applicant will submit full preliminary materials that incorporate the lot-line elimination noted for Phase 1, revised house footprints to respect wetland setbacks and the revised open-space plan. The board will revisit the site-walk and sidewalk scheduling at a future meeting when snow cover permits.