The Brentwood Planning Board voted to waive the 1,500‑sq. ft. expedited‑review limit and approved a site plan for SIGSauer Academy to replace three overhead range covers with modular wood structures, new heaters, and noise‑mitigation panels; fire‑department inspections and building permits remain required.
Get email alerts on the Land Use Site Plan topic
No spam. Unsubscribe anytime.
The Brentwood Planning Board voted to waive the town’s 1,500‑square‑foot cap for expedited site‑plan review and approved an expedited site plan for SIGSauer Academy to replace three existing range covers.
Colin Murphy, identified as senior operations manager at SIGSauer Academy, told the board the work is primarily a replacement of existing structures on ranges 8, 9 and 10. He described two of the new pads as approximately 45 by 15 feet and the third as 65 by 15 feet, with wood framing, 6x6 posts, metal standing‑seam roofs, roll‑down polyethylene sides and infrared ceiling heaters. Murphy also said the surface will remain aggregate (stone/dust) and that no new security lighting is proposed.
Planning staff flagged that the project totals about 2,100 square feet—roughly 600 square feet over the expedited‑review threshold. Planning Board staff recommended the board waive the 1,500‑sq. ft. limit to allow expedited processing. Speaker 10 moved to waive the limit and Speaker 4 seconded; the board voted in favor. The board then voted to approve the site‑plan application under expedited review, with a motion to approve moved by Speaker 3 and seconded by Speaker 9.
Board members asked technical questions about capacity and safety: Murphy said each unit would accommodate about 10 shooters plus two instructors and confirmed propane tanks shown on the plans would be moved and buried subsurface where required; he said the fire department would inspect those lines as part of the building permit process. The board noted that fire‑department signoff and the building permit remain conditions of the project’s implementation.
The board’s action waives the local expedited‑review square‑foot limit for this application and approves the application itself; staff said the notice of decision will list the applicable zoning or site‑plan regulation. The applicant may proceed to the building‑permit stage and will be subject to any inspections or conditions the town’s code requires.
The planning board did not record additional permit conditions in the meeting discussion beyond the standard building and fire inspections; the chair instructed staff to include the specific regulation citation in the written decision.