Summary
The commission unanimously recommended approval of the final plat for The Grove at Newcastle, a 16.93‑acre senior multifamily parcel of the Windermere PUD featuring 19 buildings and 120 units; staff recommended and the commission approved a variance to sidewalk requirements, and the developer will maintain internal roads and common areas.
Get email alerts on the The Grove Final Plat topic
No spam. Unsubscribe anytime.
The New Castle Planning and Zoning Commission on Nov. 27 recommended that the City Council approve the final plat for The Grove at Newcastle and granted a requested variance from the city’s sidewalk standard.
Keith Johnson, development services coordinator, told commissioners the Grove is a 16.93‑acre parcel within the Windermere Planned Unit Development (Ordinance No. 785) proposed as senior multifamily housing. The plan shows 19 buildings with about 120 dwelling units and a community center. Johnson said the applicant had addressed staff comments and requested a variance to the sidewalk requirement (cited in the staff materials as code section 153.051) because sidewalks along Garrett Drive and the north side adjacent to NW 16th Street are constrained by drainage improvements and right‑of‑way conditions.
Johnson outlined infrastructure and maintenance responsibilities: drainage and detention will be designed not to exceed predevelopment flows and will discharge to the Windermere Phase 8 detention pond; the developer will be responsible for maintenance of drainage easements and infrastructure. Sanitary sewer will tie into an existing 8‑inch public line along the site’s northern edge, and the developer will dedicate public sewer easements. Water mains are shown to meet service and fire‑protection requirements. He said internal streets, sidewalks and parking are intended to be privately owned and privately maintained; the plat will include language noting the city is not responsible for the maintenance of private drives.
Commission discussion focused on sewer routing and easements, internal street widths (staff noted a 24‑foot lane to meet fire access), parking allocations and whether the development units would be rental or for sale. Staff and the applicant confirmed the units would be rentals owned by the developer’s LLC, some perimeter units include garages, and parking was planned to meet code requirements.
A commissioner moved to recommend approval of the final plat and to include approval of the sidewalk variance; the motion was seconded and carried unanimously. The commission will forward the recommendation to City Council for final action.
Next steps: the recommendation goes to City Council; staff said that standard engineering reviews for drainage, water and sewer connections and construction details will continue before final construction permits are issued.