Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Infrastructure Pumps topic

No spam. Unsubscribe anytime.

County OKs $3.5M CMAR contract for East Elm Creek pump-station replacement

Delaware County Board of Commissioners · November 25, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Commissioners approved a construction manager-at-risk contract with Peterson Construction for the East Elm Creek pump-station replacement, a project staff said is beyond its useful life and will improve capacity; total cost cited at $3.5 million with completion aimed for 2026–2027.

The Delaware County Board of Commissioners approved a construction manager-at-risk (CMAR) contract with Peterson Construction Company on Nov. 24 for the East Elm Creek pump-station replacement.

Tiffany Magg, director of environmental services, told the board the existing pump station is beyond its useful life and requires both upgrades for capacity and relocation of flows to the new plant. Magg said the "Total cost is 3 and a half million dollars" and that the county is "looking for this to be complete hopefully by 2026, maybe into 2027." She added some early procurement is being pursued for long-lead items such as electrical equipment and a generator so construction can be fast-tracked.

Commissioners asked whether the project was budgeted; Magg confirmed costs were included across 2025 and 2026, with specific line items noted for design and construction budgeting. The board voted to approve the CMAR contract, with recorded affirmative votes from Commissioners Lewis, Merrill and Benton.