Commission grants time extension for East Adams Phase II housing project
Syracuse Planning Commission · December 2, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.
Summary
McCormack Baron Salazar asked for and received a first‑time extension for the East Adams Phase II housing project (MASPR 24‑27) to align approvals with a construction schedule now expected to complete by June 25, 2028; commission approved the extension with a condition to adhere to prior project requirements.
Extension requested and rationale: Project manager Jen Conception of McCormick Baron Salazar requested a first‑time extension for MASPR‑24‑27 (East Adams Phase II), citing project size and lender scheduling that…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat
30-day money-back on paid plans